6.4.2 Maintenance guidance. INVT XG3-10kW, XG3-10KTL Single-phase On-grid Solar Inverter
Add to My manuals40 Pages
The INVT XG3-10KTL Single-phase On-grid Solar Inverter is a grid-tied solar inverter designed for use in photovoltaic systems to convert DC power generated by solar panels into AC power that can be fed into the utility grid. It features advanced MPPT (Maximum Power Point Tracking) technology to maximize energy harvest from the solar array, and is equipped with DRM (Dynamic Reactive power Management) and CT (Current Transformer) for grid stability and power factor correction.
advertisement
Grid-tied single -phase solar inverter Running
Check Item Inspection Method
Maintenance
Cycle
Electrical connections
Cooling fan maintenance and replacement
Security function
Check whether the system cable connection is loose, whether the inverter wiring terminal is loose, and then tighten it according to the method specified in section 4.
Check whether the cable is damaged, especially whether the rubber skin in contact with the metal surface has cut marks.
For three-phase inverter products, observe whether the air inlet and outlet are normal, and check whether there are cracks in the fan blades. Listen for abnormal vibration when the fan is running. If necessary, clean the air inlet and outlet; if the fan is abnormal, it needs to be replaced in time, see section 6.4.2.
Check the inverter LCD and the shutdown function of the system. Simulate stop and check the stop signal communication. Check the warning labels and replace them if necessary.
Once per half a year
Once per half a year
Once per half a year
6.4.2 Maintenance guidance
Inverter cleaning
The cleaning steps are as follows:
(1) Disconnect the input and output connections.
(2) Wait ten minutes.
(3) Use a soft brush or vacuum cleaner to clean the surface of the inverter and the air inlet and outlet.
(4) Repeat the operation content in section 6.1.
(5) Restart the inverter.
Fan maintenance
Stop the inverter before maintenance work, and all power inputs of the inverter must be disconnected.
Wait at least 3 minutes for the capacitors inside the inverter to fully discharge before starting maintenance work.
Only professional electricians can perform maintenance and replacement of the fan.
28
Grid-tied single -phase solar inverter Running
Step 1: Stop the inverter and disconnect the electrical connection.
(1) Disconnect the input and output connections.
(2) Turn the DC switch to the "OFF" position.
(3) Wait ten minutes.
(4) Disconnect all electrical connections at the bottom of the inverter.
Step 2: Disconnect the fan power plug and remove the fan cover at the bottom of the chassis.
Step 3: Use a soft brush or vacuum cleaner to clean the fan. If the fan is damaged, follow step 4.
Step 4: If the fan is damaged, remove the damaged fan and install the good fan to its original position.
Step 5 : Re-install the fan tray to the inverter in the reverse order and restart the inverter.
。
Note
Once the inverter stops due to an alarm, it is prohibited to start the inverter immediately. You should find out the cause and confirm that all faults have been eliminated before starting the inverter. The inspection should be carried out strictly in accordance with the steps in section 6.1.
29
advertisement
Related manuals
advertisement
Table of contents
- 5 1. Safety precautions
- 5 1.1Warning marks
- 6 1.2 Safety guidance
- 7 1.2.1 Transport and installation
- 7 1.2.2 Grid-connected operation
- 8 1.2.3 Maintenance and inspection
- 8 1.2.4 Waste disposal
- 9 2 Product overview
- 9 2.1 PV grid-connected power generation system
- 10 2.2 Product appearance
- 11 2.3 Nameplate description
- 12 2.4 Product model
- 13 2.5 Outline dimension and weight
- 14 2.6 The LED light panel
- 14 2.6.1 The LED light panel
- 15 2.6.2 LCD operation panel
- 16 2.7 Bottom of the inverter
- 17 3 Inverter storage
- 18 4 Installation
- 18 4.1 Unpacking confirmation
- 20 4.2 Prepare before installation
- 20 4.2.1 Installation tool
- 20 4.2.2 Installation environment
- 21 4.3 Space requirements
- 22 4.4 Mounting board size
- 23 4.5 Wall installation
- 23 4.6 Install the inverter
- 25 5 Electrical connection
- 25 5.1 Overview of electrical connections
- 25 5.2 Connect the protective ground wire
- 26 5.3 Connection of PV string
- 28 5.4 Connection of DRM & CT
- 29 5.5 Single-phase inverter grid access
- 30 6 Running
- 30 6.1 Inspection before running
- 30 6.2 Inverter grid-connected running
- 31 6.3 Inverter stop
- 31 6.4 Daily maintenance and inspection
- 31 6.4.1 Periodic maintenance on the inverter
- 32 6.4.2 Maintenance guidance
- 34 7 Troubleshooting
- 38 8 Contact information
- 39 9 Appendix